Sunday 7 April 2013

Day 109

Apr. 05  2013
Today we have received the pre-plaster inspection result, there're still 20 defects, in which 9 of them being legacies of frame inspection, 11 new finds. Not sure how they can be re-inspected before covering plaster, looks like the plaster will be going up very soon…Nonetheless, we’re quite happy with the progress of the build, credit to our SS.

Thursday 4 April 2013

Day 107

Apr. 04  2013
Today we confirmed with our SS for the pre-plaster inspection date, all the defects discovered in frame inspection will be revisited, fingers crossed.


Day 102

Mar. 30 2013

Day 98

Mar. 26  2013
Brick started, realy pleased by the color and free mortar selections.


Day 87

Mar. 15  2013
House fully wrapped.
 

Day 78

New Home Inspections
Mar. 06  2013

Today we received our first inspection result, to our surprise, we got 17 defects. However considering we did the frame inspection slightly before frame completion, all the defects shall be revisited in the pre-plaster inspection.



Day 73

Mar. 01 2013
Gutters' up


Wednesday 3 April 2013

Day 71

Feb. 27 2013
Trusses're up, near frame completion.


Day 70

Feb. 26  2013
1st floor framing started.Windows delivered.


Day 58

Feb. 14  2013
Ground level framing started, joists delivered.


Between Site Start and Base Completion

Feb.06 2013
Base completed, invoice received.



19/12/2012

While we were away on holidays, received a call from our assigned site supervisor Dean. Feels like Dean is very professional with the job and he is quite good at progressing the build quickly.

Nov. 6 2012 Demolition Completed

Demolisher: Vic Wide Demolition
Duration:6 weeks

The machine was onsite for 2 weeks but could not get the job moving due to demolition certificate delay.